Jump To Navigation

Understanding Contract Termination

By John T. Trout, Esq.

What does it mean to terminate a contract?

To terminate a contract means to end the contract prior to it being fully performed by the parties. In other words prior to the parties performing all of their respective obligations required by the contract, their duty to perform these obligations ceases to exist.

In general, the effect of the termination of a contract is to discharge the parties from their unperformed obligations under the contract. However, termination does not affect liabilities of the parties for breaches of the contract that occurred prior to the contract being terminated. And, despite the fact that future obligations to perform under the contract terms have been extinguished, if appropriate, the parties remain entitled to pursue claims for damages under the common law and as provided by any termination provisions that may be contained within the contract.

The right to terminate.

There are two basic types of termination: 1) termination for cause, otherwise known as termination for default; and 2) termination for convenience. A party's right to terminate its contract may originate from the general principles of contract law or it may arise out of the terms of the contract itself. On the other hand, termination for convenience may originate only from the terms of a contract which provide for such termination, for there is no general contract principle allowing termination for convenience. A termination for cause is available only in response to a material breach of the contract by the other party. What qualifies as a material breach to the contract may be determined by a review of the contract case law or what qualifies as a material breach or default may be stated in the contract itself. A failure to perform any contract term is a breach of the contract. However, substantial damages are recoverable only from a material breach and a material breach entitles the non-breaching party to treat the material breach as a breach of the entire contract. Whether there has been a material breach depends upon the seriousness of the breach and the likelihood that the injured party has, nevertheless, received substantially what it had contracted to receive under the contract. The extent of the monetary damage suffered by the non-breaching party is not necessarily determinative of material breach. Materiality of the breach must be determined on a case-by-case basis and in light of the purposes for which the party entered the contract.

The following facts are considered by courts in determining whether a breach was material:

  1. Was there a failure of an essential feature on the contract which had induced the non-breaching party to enter the contract;
  2. Did the breach go to the substance of the contract and defeat the non-breaching party's purpose for making it;
  3. Did the breach affect a matter of vital importance going to the essence of the contract;
  4. Did the non-breaching party receive substantially less or different from that which he had bargained to receive?

Steps to proper termination.

The terms of the contract itself sometimes identifies the conditions under which a party may be found in material breach or default or conditions under which a party may terminate for convenience. Service of notice and proper completion of other procedural requirements necessary for termination under the contract terms must be followed exactly. Otherwise, the termination might not be authorized by the contract and therefore be a wrongful termination.

Although termination under general principles of contract law does not specifically require prior notice and an opportunity to cure, providing notice and opportunity to cure may prompt the defaulting party into curing the default and will place the non-breaching party in a more favorable light should the dispute end up in arbitration or litigation. And, cure of the breach or default is usually preferable to termination and the often accompanying legal action.

Wrongful termination.

In the event a party terminates the contract without having justification either under general principles of contract law or under the terms of the contract, such a termination is called a wrongful termination. A wrongful termination is a repudiation of the contract, and is therefore in itself a material breach of the contract.

Damages related to termination.

Damages available to the non-breaching party following its termination of the contract or in response to a wrongful termination by the other party include direct damages, consequential damages, and all other damages necessary to place the non-breaching party in the same position it would have been in should the contract have been completely performed by the parties. In the context of a contractor wrongfully terminating its contract with an owner, the owner would be entitled to recover from the contractor the costs of hiring a replacement contractor to finish the Work, costs associated with delay of completion of the project including lost profits from use of the completed project, any additional costs for completion due to the termination, and any additional costs related to administration of the project, including additional costs for project management.

On the other side, in response to an owner's wrongful termination of a construction contract, the contractor would be entitled to recover the cost of its work to the point of termination plus all overhead incurred, plus lost profits and overhead. In the event of an owners' wrongful termination of the contractor following substantial completion, the contractor would be entitled to recover the contract amount less the actual cost the contractor would have incurred in completing the balance of the project.

Conclusion

Contract termination is a drastic step and should be avoided, if possible. However, there are times when termination is appropriate, such as when the terms of the contract or the law allow for termination and it would also be the best way to mitigate damages. Under these circumstances, the contract should be terminated with caution and with good legal advice.

Firm Highlights

Our attorneys have consistently been named Super Lawyers© and Rising Stars© in the legal profession by Minnesota Law & Politics, Mpls St. Paul Magazine and Twin Cities Business Monthly. Hellmuth & Johnson is AV® Peer Review Rated – the highest possible Peer Review Rating from Martindale-Hubbell – indicating our dedication to professional excellence and adherence to the highest ethical standards.

Hellmuth & Johnson has since grown into one of Minnesota's top twenty-five largest law firms, positioning us to provide a full suite of services to clients without sacrificing our original commitment to providing responsive and affordable representation. Our clients span the spectrum from a first-time home buyer to community associations, construction companies and international corporations.

In The News / Read All

January 2012 - Hellmuth & Johnson Adds Two New Attorneys

November 2011 - Hellmuth & Johnson Adds Two New Attorneys

September 16, 2011 - Hellmuth & Johnson was selected as the 2011 MADACS Product Service Member of the Year by the Minnesota Multi Housing Association. Phaedra Howard, Esq. accepted the award on behalf of Hellmuth & Johnson at the MADACS Awards ceremony on September 16th.

Contact Us Today

Bold labels are required.

Contact Information
disclaimer.

The use of the Internet or this form for communication with the firm or any individual member of the firm does not establish an attorney-client relationship. Confidential or time-sensitive information should not be sent through this form.

close
Seminars & Events / Learn More

We provide the highest quality legal services delivered in a responsive cost-effective manner by experienced professionals who understand your needs.

Click here to learn more about our upcoming events.

Privacy Policy | FirmSite® by FindLaw, a Thomson Reuters business.